ALL ISLAND PROJECTS
AS OF 5/31/11
ID
Task Name
Duration
Start
Finish
June
I Ju
August
5/22 I 5/29
6/5
6/12 I 6/19 1 6/26
IB
7/3
I 7/10 I 7117
7/24
7/3“
Flagpole Pool
91 days
Sun 5/29/11
Fri 9/30/11
2
Main House Pool
97 days
Sun 5/29/11 Mon 10/10/11
3
Cottage #4
97 days
Sun 5/29/11 Mon 10/10/11
Relax Room
11 days
Sun 5/29/11
Fri 6/10/11
4
5
Relax Restroom
60 days
Mon 6/13111
Fri 9/2/11
6
Paint Desal
30 days
Mon 6/13/11
Fri 7122111
7
7
Desal Roof Waterproofing
20 days
Mon 7/25/11
Fri 8/19/11
8
Mechanical Sitework
40 days
Mon 8122111
Fri 10/14/11
9
10
Decommission Mechanical
25 days Mon 10/17111
Fri 11/18/11
11
12
Terrace Wall
40 days
Sun 5/29/11
Thu 7/21/11
Terrace Sea Wall
30 days
Fri 7/15/11
Thu 8/25/11
13
14
Upper Terrace
30 days
Mon 8/8/11
Fri 9/16/11
15
Roundabout
30 days
Fri 8/26/11
Thu 10/6/11
16
Casket-Intersection Road
30 days
Fri 10/7/11
Thu 11/17/11
17
Flagpole Road
30 days
Fri 10/14/11
Thu 11/24/11
18
Helipad Road
20 days
Fri 11/25/11
Thu 12122/11
19
20
Five Palms
91 days
Mon 8/1111
Mon 12/5/11
21
Dock Shelters
40 days
Mon 9/5/11
Fri ionwii
22
Managers Cottage
60 days
Mon 8/22/11
Fri 11/11/11
23
24
East Shelter
30 days
Mon 10/3/11
Fri 11/11/11
25
Staff Restroom
40 days
Tue 10/11/11
Mon 12/5/11
26
Helipad Wall
20 days
Mon 9/5/11
Fri 9/30/11
27
Top of the Hill
70 days
Mon 8/1/11
Fri 11/4/11
Task
Milestone
•
External Tasks
Protect: All Jobs Schedule 29 June11
Date: Fri 7/1/11
Split
Summary
•
•
External Milestone
Progress
Deadline
Project Summary
Page 1
EFTA_R1_02035479
EFTA02692737
ALL ISLAND PROJECTS
AS OF 5/31/11
I September
9/25
October
November
I
8/7
1 8/14
1 8121
8/28
9/4
1 9/11 f 9/18
1012
1 10/9
1 10/18
10/23 1 10/30 1 11/8
11/13 11 11/20 1 11/27
12/4 1 12/11 1 12/15 1 12/25
1
---
l.
r i
i
1‘
Project: All Jobs Schedule 29 June11
Date: Fri 7/1111
Task
Split
Progress
Milestone
Summary
Project Summary
♦
••
External Tasks
External Milestone .
Deadline
.
.
Page 2
EFTA_R1_02035480
EFTA02692738
Technical Artifacts (4)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Phone
2692737Phone
2692738Phone
7122111Phone
8122111Forum Discussions