Project Costs in Total
8,548,000.00 Hard Costs
671,000.00 Change Orders
2,595,000.00 Soft Costs & FF&E/OS&E Costs
1,300,000.00 Shortfall Reserve Replenishment
247,000.00 Operating Costs
500,000.00 Restaurant Loan
13,861,000.00
Funding in Total
1,220,773.60
6,474,755.53
1,275,470.87
2,070,000.00
2,000,000.00
820,000.00
13,861,000.00
DM Reimbursable (est.)
Building Loan
Project Loan
1st Round of Investor Loans
2nd Round of Investor Loans
Equipment Capital Lease
Project Costs to Date
6,558,000.00 Hard Costs
235,000.00 Change Orders
1,845,000.00 Soft Costs & FF&E/OS&E Costs
1,300,000.00 Shortfall Reserve Replenishment
247,000.00 Operating Costs
346,000.00 Restaurant Loan
10,531,000.00
Funding to Date
1,220,773.60
5,765,755.53
1,274,470.87
2,070,000.00
200,000.00
0.00
10,531,000.00
DM Reimbursable (est.)
Building Loan
Project Loan
1st Round of Investor Loans
2nd Round of Investor Loans
Equipment Capital Lease
Project Costs Remaining
1,990,000.00 Hard Costs
436,000.00 Change Orders
750,000.00 Soft Costs & FF&E/OS&E Costs
0.00 Shortfall Reserve Replenishment
0.00 Operating Costs
154,000.00 Restaurant Loan
3,330,000.00
Funding Remain
0.00
709,000.00
1,000.00
0.00
1,800,000.00
820,000.00
ing
DM Reimbursable (est.)
Building Loan
Project Loan
1st Round of Investor Loans
2nd Round of Investor Loans
Equipment Capital Lease
3,330,000.00
Note: All numbers are approx., 1st round of investor loans paid off upon loan modification and reimbursables as of 5/17/17 was 5991,689
EFTA00615091
Forum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.