Zorro Projects - 5/4/13
Main House - Outside
Start
End
Total Est. Cost
Notes
Landscaping -
Proposals & Maintenance from 3 companies forwarded to RK &
Rear Planter Bed
DI - 3/28/13
Front & Rear Parking Beds
Bowel Garden
'JE approved 4/27/13, Aspen Landscaping received the contract to
refurbish.
Aspen Grove
New proposal received 5/3/13 will review & forward 5/6/13
Pinion Screen
Landscape Lighting Timers -
;JE approved 4/27/13 to replace Timers
Landscaping - In House -
JE approved 4/27/13 to remove existing Ponderosa Pines,
Landscape Lights & to relocate Pinions to the area.
Ponderosa Pines & Landscape Lights at
Front Entrance
Removal of Dead Pine in Front Courtyard.
CAN WE PROCEED WITH REMOVAL
Bid Received 12/12/12 - Approved 3/20/13
Terraces - Three B's
4/7/13
$56,200.00
Terraces - $52,000.00
Stucco/Gutters/Painting - $4,200.00
Library Terrace Membrane - installed. Stucco to be completed
once MBR Terrence membrane is installed
MBR Terrace Demo complete. Work continues
$36,400.00
'Bid
Stucco Work - Three B's
4/7/13
Received 3/1/13 - Approved 3/20/13
Site Walls
Wall Stucco Patching & Painting 90% complete
Columns
Columns Stucco & Painting 90% complete
Attached Photos
Estancia Fountain -
$2,500.00
Bid received 3/1/13
Bowl Lift - $1,220.00
JE approved 4/27/13
Electrical - $880.00
Pump - $400.00
4/29/13 - Brice determined that the leak is the main line going to
the upper bowl. Proposed repair is to isolate leaking line & use
return line to lower bowl, splitting line to feed upper bowl. This
will mean we will continue using existing pump & filter. Will
forward cost 5/9/13
EFTA00624854
Zorro Projects - 5/4/13
Chess Fountain -
Requires resurfacing
JE approved 4/27/13
Bid will be forwarded 5/10/13
Ranch Front Gates -
Received bid 4/20/13, have requested vendor to make
adjustments, new bid received 5/3/13, reviewing
JE approved 4/27/13
New Gate Openers
Main House - Inside
Start
Total Est. Cost
Notes
Cooling Tower -
4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded
Replacement of Pool Pac -
9/11/12
4/29/13 - Quote forwarded to RK, who requested more detail,
will forward once in hand
Engineering Inspection - $5,000.00
Unit Cost - $43,170.00
Ducting - TBA
Re • air of Pool Pac -
3/15/13
Unit working on fan only, proceeding with replacement of Pool
Pac
Repair Pool/Spa -
Vendor on site 4/8/13 to review scope of work
Water Sample of Tap Water -
4/27/13 - JE requested water samples be taken.
This will be completed by the end of the coming week once water
system is balanced - Dakota Well/RO went on line 5/3/13
Exterior Doors -
JE requested 4/27/13 that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
Audio Upgrade -
Installed - final programming required
Installed - Programming of remotes required
New TV's
DVD Players/Theater Upgrade
EFTA00624855
Zorro Projects - 5/4/13
Kitchen Table Electrical - Three B's
Bid Received 3/1/13 Lead Time 1 Week
Need to review design and floor
Electrical & Data Cut In - $2,160.00
Media Room - New Curtains/Blackout
2/24/13
JE selected fabric 4/27/13. Amount required has been placed on
hold. 2 companies will be submitting a bid by 5/9/13
Sarah's Office - New Curtains/Lined
2/24/13
JE selected fabric 4/27/13. As of date manufacturer cannot
provide enough yardage, they will forward an update 5/6/13
Gym - Mirrored Doors - Backed/Framed
2/24/13
3 B's completed, JE requested further work, will review with
vendor
IT & Phones
Start
End
Total Ed. Cost
Notes
4/27/13 JE approved the installation of new phones at MH
Reviewing new scope of work - Microwave option
Cell Repeaters & WI-Fl
Start
End
Total Bt. Cost
Notes
Cell Repeater - Library
Will have installed by 5/9/13
Cell Repeater- Gym
Will be completed with Audio install
Sound System - Gym
Requires refurbishment to accept I Pad
Computers
Lap Top - Lodge
Desk Top - Office
REQUESTING APPROVAL TO PURCHASE
Well K
Start
En
Total Est. Cost
Notes
Plugging First Hole - $15,000.00
Multi Media Filters & Install - $5,844.57
Transponder & Install - $1,700.00
Mis Pipe & Fittings - $1,000.00
Windows Laptop - $700.00
4/27/13
5/3/13
$620.56
JE approved 4/27/13
5/3/13 - Multi Media Filters ordered
5/8/13 - Transponder to be installed
5/3/13 - Laptop purchased
Dakota RO Water Softener
Start
End
Total Ed. Cost
Notes
2/18/13
5/3/13
$3,045.45
Complete - Well & RO on line as of 5/3/13
Lodge
Start
End
Total Est. Cost
Notes
Roof - Repair/Replace Broken Sections
11 will complete while on site for upcoming projects
EFTA00624856
Zorro Projects - 5/4/13
Log Cabin
Start
End
Total Est. Cost
Notes
Step Outside - Repair/Replace
2/24/13
NA
Caboose
Start
End
Total Est. Cost
Notes
Outside Wall - Installation of Retaining Wall
NA
Yurt
Start
End
Total Est. Cost
Notes
Yurt - Replace Walls/Roof/Door/Windows
$6,355.00
plus shipping
charges of
approx. $480.00
JE approved 1/12/13.
Vendor forwarded quote 5/3/13 - lead time after payment 8 to
10 weeks.
Floor will need to be sanded and resurfaced
REQUESTING APPROVAL FOR 50% DEPOSIT
Flay Barn
Start
End
Total Est. Cost
Notes
Paint
4/8/13
NA
Work to begin 5/9/13
Greenhouse
Start
End
Total Est. Cost
Notes
Paint-Outside
3/24/13
4/29/13
$390.00
Complete
Bunkhouse
Start
End
Total Est. Cost
Notes
Paint - Window Frames & Sills
2/24/13
NA
Walls completed, working on window frames & sills
Window/Doors - Total Replacement
2/6/12
Will Budget for 2014
Reservoir
Start
End
Total Est. Cost
Notes
Paint - Tank
2/24/13
NA
Will start once Bunkhouse & Haybam complete
Vehicles
Start
End
Total Est. Cost
Notes
2013 Ford Expedition - review Captain Seats
to be installed
3/27/13
Estimate received 5/2/13 - $11,528.74
Awaiting 2nd estimate
2008 Dodge Dually -Service/Repair
$3,509.55
Complete
M2
Start
End
Total Est. Cost
Notes
JE approved 4/27/13 investigating purchase of 2 dogs.
Researching
EFTA00624857
Zorro Projects - 5/4/13
Purchases
White Rug - Gym (10 x 12)
JE approved 4/27/13 to move ahead with Robert's Flooring to
manufacture a rug using carpet. Estimate expected 5/10/13
Big Urns - Outside MH
JE approved 3/27/13 - Terre Cotto
Outside Pool Furniture
Large Chrome Pool Clock
Facial Machine
Sue & Karyna to purchase
EFTA00624858
Technical Artifacts (2)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Wire Ref
refurbishWire Ref
refurbishmentForum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.