From: Nice gordon •tta
To: J <jeevacation®gmail.com>
Cc: Rich Kahn
LSJ GSJ
Subject: LSJ RO Sea Water Intake Pumps Replacement
Date: Fri, 19 Oct 2018 13:36:32 +0000
Attachments: LSJ_Gem_Intake_Pumps.pdf; LSJ_SW_Pumpsjpg
Good afternoon
As discussed attached for your review
Proposal from Gemini Sea water Systems to replace existing original RO Sea Water Intake Pumps. Cost for Material and Installation
$75,310.00
Photo's of existing original Sea Water Intake Pumps.
The Existing Sea Water Intake Pumps are original to the install of the 90k SWRO Plant.
This System was designed for 2 x SWRO Plants, only one plant was installed, hence 4 pumps.
The Existing Intake System requires only one pump to supply the 90k SWRO Plant
The Expanded SWRO Plant will require 2 of the 4 pumps.
At this time 2 of the 4 pumps/motors and the priming pump/motor need replacing, therefore we have no redundancy.
The attached proposal is for 2 x 15hp motors with S/S fluid ends with VFD's and Priming Station, I pump to supply SWRO, 1 as a
redundancy. New piping, valves, S/S strainer baskets are also included in cost
4 week lead-time for Pumps once ordered
how do you wish to proceed
regards Brice
Brice Cordon
The Saint James Group
USVI
Ph:
EFTA01019179
Technical Artifacts (1)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Domain
gmail.comForum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.