To:
JEE[[email protected]
From:
curtis
Sent:
Thur 4/30/2009 7:45:39 PM
Subject: Revised Mechanical budget
04-17-09-LSJ- MechBldaUpdate FINAL.pdf
Title: Revised Mechanical budget Jeffrey,
Please find attached Revised Mechanical Building Budget for you approval
The Original Budget was 2,330,543.72 in Green font
Adjustments total
-$317,858.67 n oink font
The revised budget is
2,012,685.05 in Blue font
Paid to date
$940,413.62 in red font
This is the original approved budget updated to show latest cost revisions based on adjustments both up
and down in individual line items showing present cost down by $317,858.67.
NOTES:
1. Newman & Moll will complete their contracted work in less than a month.
2. The contract was bought out for $689,000, leaving $20,500 remaining in the budget. (see line 3120)
3. We recommend using this money towards the 1,000 gallon DPNR required Gasoline tank
containment vessel.
4. This will serve two purposes
A. Satisfy the DPNR for this requirement.
B. Keep Newman & Moll on site a couple more weeks, as we review Final Mechanical Build Out
Options, thus avoiding re-mobilization costs, if we Newman & Moll for future work.
Or
We can reconcile the concrete by deducting $20,500 off this budget now and let them finish.
Curtis
EFTA_R1_01516848
EFTA02442071
Technical Artifacts (2)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Email
[email protected]Phone