PROGRESS REPORT
Estate Manager
2/23/01 through 3/6/01
GENERAL
Spent 2+ days at Zorro, NY office and PB receiving an overview of the operation
and meeting with staff.
Toured 71m Street with Ms. M receiving an overview of the operation and met with
staff. Toured 65th receiving an overview of construction and future facility use.
Visited the Morikami Japanese Gardens and met with Randy Keshock
IM) the horticulturist and supervisor of maintenance. He has worked for the
parks department 5 years and has been responsible for the Morikami Gardens for
the past two years. He and his staff (of 4) are self taught and did not have
experience in Japanese gardens prior to receiving these positions. He does part time
design work on the side but doesn't know anyone with expertise in this area who is
looking for a full time position.
PALM BEACH
Coordinated with 7 agencies to receive resumes for potential couples/single for PB
estate. I will also meet with several agencies at the Denver Conference later this
week.
Met with Ms. M regarding areas of concern and tasks that were not completed or
not acceptable. She requested I focus on upgrading standards and initiate
additional task lists. I received and logged tasks from both Ms. M and Mr. Epstein.
I completed an exterior and cabana inspection and logged approximately 100 tasks
needing attention. I'll focus on the interior tomorrow when
are on site. I'll have the opportunity to assess their skill
level.
Met with Frank Steele regarding staff housing project. Gained an understanding of
scope of work and landscape needing relocation. John and I will meet with
landscapers to coordinate work and receive quotations. Frank is to provide a list no
later than 3/7/01 of interior finishes which need to be selected.
Spoke to Mike Johnson regarding the staff housing. He will provide a
planning/construction schedule showing now through the completion of the project
no later than 3/8/01.
EFTA00577872
Developed a tracking system for tasks and initiated at Zorro to fine tune before
initiating at other locations. Will be visiting Zorro next week to develop this system
and then initiate it at PB and LSJ.
LSJ
Coordinated the schedule of the bedroom roof/AC project with Frank
Steele...memorandum attached.
EFTA00577873
Related Documents (6)
DOJ Data Set 11OtherUnknown
EFTA02444115
1p
DOJ Data Set 9OtherUnknown
From: Lesley Groff
1p
Dept. of JusticeOtherUnknown
EFTA Document EFTA01398793
Subject: RE: MD approval for ACUs completed for High Risk Clients [I] From: Andrew Gallivan Date: Fri, 07 Apr 2017 To: Vaishali-P Mehta < Classification: For internal use only Approved. From: Vaishali-P Mehta Sent: Friday, April 07, 2017 2:21 PM To: Andrew Gallivan Subject: FW: MD approval for ACUs completed for High Risk Clients [I] Classification: For internal use only Hi Andrew, In an effort to ensure that you have to approve only 1 email, I sent the below email, in hindsight I s
43p
DOJ Data Set 9OtherUnknown
From: "Jeffrey E." <I
2p
DOJ Data Set 10OtherUnknown
EFTA01964238
3p
DOJ Data Set 9OtherUnknown
October 5th, 2014
5p
Forum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.