JE Punch List —August 10, 2012 Directive Updates

Date
Unknown
Source
DOJ Data Set 9
Reference
efta-efta00584276
Pages
3
Persons
0
Integrity
No Hash Available

Summary

Ask AI About This Document

0Share
PostReddit

Extracted Text (OCR)

EFTA Disclosure
Text extracted via OCR from the original document. May contain errors from the scanning process.
JE Punch List —August 10, 2012 Directive Updates 1. Clean Up - make as many barge runs as necessary - Top of Desal plant - Engineering - Cleaning the shops — ongoing 2. Equipment and Vehicles - Sell equipment - Bikes should be ready to be sold — no sales without JE approval — bike sale list forwarded to Brice 7/24 - will be forwarded for JE approval - No machinery off the island unless approved - Buy new Kawasaki bikes and mules — (4) 2012 Kawasaki 750 EPS and (2) 2012 Kawasaki Mule 4010 — ordered — EDA to Tropical 8/15 — booked to sail on 8/17, EDA on STT 8/21 - Kawasaki parts order — credit from (1) 2012 Kawasaki 750 EPS — Brice and Larry to review 3. Old Road Down to Engineering —Jules to start removing very carefully — the one that the cement cow was removed on — there is a major power line running through that ramp —Jules to now grade that road out as best as possible - COMPLETE 4. Computers - Buy new computers — 2 Macs Desktops & 1 Laptop — Captains' Office - ordered 5. Five Palms - Internet/Phone Switch installed — broken fiber discovered 7/24 —Danny to complete repairs beginning 8/13 — Danny will discuss with - Exterior Door Shutters — Pro-Tekt estimate forwarded to JE 7/12 - $2,865.00 - awaiting direction - Painting - outside to be completed via JE direction - Statue — one of them damaged — awaiting JE direction regarding repairs - Furniture — outside furniture on LSJ 8/3 - furniture in storage waiting to be set up on 8/13 —Daphne per JE - Piano — schedule to re-tune week of 8/15 - Picture Frame — measurements forwarded ta 86 x 70 - Mirrored siding — liquid nails — will cover entire panel with glue when the next one falls off - Transformer Protection Shelter — should be built — Clement/Benny to start on 8/14 — Danny will discuss with - Floor Gold Lamps - electrical wiring needs to be replaced - COMPLETE - Fire pit — fix — a new propane tank was installed but it is now empty - Dann -id Brian suspect there is a leak - they will replace the piping — Danny to start on 8/15 — Danny will discuss with 6. Grotto - Curtains — existing color not available — awaiting swatches for JE review - Genset wiring — COMPLETE - Danny reviewing auto start from Kite House — need to purchase an electronic remote car starter from Electronics Unlimited — special ordered 8/10 — EDA on STT 8/17 7. Berm/Top of Hill - Inside rock removal and clean up — COMPLETE — hydroseed inside 8/13 - Outside rock removal and clean up — begins 8/14 8. Engineering/Maintenance Yard - Engineering Bays — paint/epoxy floor/clean up — in progress - per JE direction by 8/14 - Engineering Doors — frames in place — doors hung — painted and caulked — plaster work in progress - Engineering Storage & Shelving — COMPLETE - Engineering shed outer wall — COMPLETE 9. Triangle - - Peter transplanted 3 palms from engineering per JE directive 7/26 — COMPLETE 10. Flagpole Pool Cabana - - Furniture — investigate new desk, new furniture more like Pool Cabana HI - relocate orange sofa to Media Room - Check water pressure in shower — Danny discovered the pressure equalizer tank was not pressurized — he pressurized and adjusted — COMPLETE EFTA00584276 11. Floating Dock - Jet ski bumpers — Carlos to complete installation - Table/Dock Box - Dock box top to be resurfaced — Danny to discuss start date with Karen - Swim Ladder — direction from JE on placement required - Dive Platform — require construction details 12. Entry Tree Lights — Lights on site, electrical installation - COMPLETE 13. Solutions for Generators — Soundproofing Installation — back wall and door — COMPLETE — JE is concerned may not be adequate for deep sound penetration 14. Tiki — Shields — EDA on STT 8/14 15. Kite House — relocate outside furniture from 5 Palms now that new 5 Palms furniture on site 16. Chillax Room — requires furniture piece for electrical/media equipment a 17. Chillax Bathroom - require blue rugs for bathroom & vanity area = 18. Mechanical Building - Replacement Transformer — estimated date to be shipped from factory (Illinois) 8/21 19. Boats - Lady G — sell — in hurricane storage 7/18 - Lady K — sell — survey forwarded to Darren & Rich, suggested price $225,000 - Big N — repair —JE approved "to keep" repair budget of $43,843 — Brice determines when project begins - Little C - new engine has a blown head — Offshore to run through warranty — boat hauled out 8/2 and damaged engine removed - delivered to Offshore to begin the process 8/3 — new engine ordered, two weeks for delivery — one day potentially in dry dock at Independent Boatyard for new engine install — Carlos will contact Fred on 8/13 for update 20. Timers - Review installing timers on air conditioners, irrigation water systems, and lights - Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas — they remain at 85 degrees - Intermittent irrigation week of 8/6 — no consistent rainfall 21. Beach lighting — per JE, replace existing transformers for the beach lighting of palms around the salt pond and beach 22. Transient Surge Protection — will review and forward estimate ASAP — Danny to discuss wit= 23. Ice Maker — on LSJ 7/25 — per JE, install and remove old one from island 24. Landscaping - Finish sundial corner (trees, stones, hydro-seed) — new trees to replace dead ones — once backhoe repaired 25. Solar lights — place every 30 feet — on LSJ 7/31 — on hold — JE wants to oversee the placement 26. Roads — grade - Jules work continues 27. Library - Lights on bookshelves need attention — Danny to discuss start date with 28. New Employee Bathrooms 29. Gym - New punching bag — arrived at 71" — will come down on the next plane trip - Subwoofer — torn or blown — Scott to research a replacement speaker — photos and information sent 8/3 30. Benches 31. Danny Vicars — boat driving lessons ongoing 32. Beach Office - complete electrical overall required - waterproofing/sealing/painting/replace rotten wood required EFTA00584277 33. LSJ Mooring — Darren will forward to Army Corp for final approval — 7/12 34 Hangar - Jermaine to redo internet at hangar — began wire clean up 8/9 — complete by 8/11 - forwarded quote for rack enclosure to Rich and Larry 8/10 — awaiting approval - Fuel Containment Pad — draft approved with drainage incorporated, waiting for updated plan 35. Master bedroom area — add many lights in master bedroom planter — Danny 7/26 — COMPLETE 36. Hurricane Season preparations - Palms tied down — rebar installed for palms on ocean side 8/6 — rope tie down 8/7 — COMPLETE - Shutters secured — in progress - Kite house security — in the event of a storm, the openings will covered with plywood 37. Office trailer — off island 8/10 38. New waste bins — (2) 20 yard bins purchased 7/26 — delivery to Tropical by 9/4 39. Logitech Universal Remote and Extenders - Jermaine programmed and installed in kitchen 8/10 EFTA00584278

Forum Discussions

This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.

Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.