To: WE LLC
Attn: Rich Kahn
Dear Mr. Kahn,
Please see the project cancellation costs below;
• Work Performed
Date: May 27, 2016
Re: Project Cancellation
Costs
Project: Asphalt Paving
Little Si James Island
o
o
o
45 trucks materials hauling @ $400.00 per
884 tons agg. base loading and spreading
884 tons agg. base structural compaction
Subtotal
Overhead 15%
$18,000.00
2,652.00
4 420.00
$25,072.00
$3,760.80
Total
$28,832.80
•
Mobilization Costs (3 times)
o Personnel — 96 man hours @ $45.00 per
$4,320.00
o Equipment Transportation — 21 @ $350.00 per
7,350.00
o Specialty Equipment shipping, taxes, clearing
4 120.00
Total
$15,790.00
•
De-mobilization Costs (3 times)
o Personnel — 96 man hours @ $45.00 per
$4,320.00
o Equipment Transportation — 21 @ $350.00 per
7.350.00
Total
$11,670.00
•
Cancellation Costs 15% $512,500.00
$76,875.00
Total Costs
$133,167.80
1
Project Cancellation Costs
LSJE LLC
EFTA00593657
Forum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.