From: Richard Kahn
To: "Jeffrey E." <[email protected]>
Subject: Fwd: Zorro Ranch Asphalt Paving
Date: Tue, 31 Jul 2018 17:52:25 +0000
Attachments: 20/TO Ranch_Revised.pdf
attached is paving proposal from Universal totaling $660,767.50 (not including 7.125% tax, bond, testing and
permits) to pave the following areas:
Main Entrance drive from State highway 41 to gate at ranch complex
Paving around Ranch buildings and garage area
Pave Road from Ranch complex to main house
Resurface existing paved road at main house
Pave road towards well house
(see sketches on pages 4-8 of PDF)
Note same bid was 643,013 on June 28, 2017
Please advise on the following:
a) scope of work above is accurate
b) are width of roads, gravel bases and asphalt bases proposed on pages 2 and 3 of PDF ok?
c) price i should try to negotiate to noting asphalt will be purchased locally as opposed to ABQ
d) start date of august 13th ok?
e) terms of 40% down
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue 4th Floor
New York, NY 10022
tel 212-971-1306
fax 212-320-0381
cell 917-414-7584
Begin forwarded message:
From:
Subject: Fwd: Zorro Ranch Asphalt Paving
Date: July 31. 2018 at 1:18:26 PM EDT
To: Rich Kahn <
Cc: Zorro Ranchi
>
as requested
EFTA01004312
Forwarded message
From: Gilbert Luna <I
Date: Tue, Jul 31, 2018 at 1:16 PM
Sub'ect: Zorro Ranch As halt Pavin
To:
Cc: Matt Luna
Hello Mr. Gordon,
Attached is our proposal for the asphalt paving improvements at Zorro Ranch. Our schedule would be to start
on August 13, 2018 and complete the work in eight weeks. Our price is based on purchasing the asphalt mix
from Mountain States Constructors in Moriarty, NM. They have a hot mix asphalt plant set up there to take care
of the paving project on NM 41 by the ranch. However, they can not guarantee that the plant will still be there
after October, so it is imperative to get started on the project soon. The cost of asphalt cement has been rising
lately and to bring in material from our regular supplier in Albuquerque would add approximately $ 40,000.00
to the cost. Our payment terms are as follows: 40% down payment upon mobilization. Monthly pay requests
submitted on the 30th for percentage of completion of the balance ( Net 15 days ). Final billing of 5% of the
contract amount due upon inspection and acceptance by you. Thank you for your consideration and please
contact me if you have any questions.
Regards,
Gilbert A. Luna
President
3825 Academy Parkway North,M.
Albuquerque, NM 87109
Cell Phone 505-401-4277
Phone: 505-884-0400
Fax: 505-344-8646
Stanley, NM
LSJ-GSJ, USVI
Ph: (505) 934 2809
EFTA01004313
Technical Artifacts (10)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Email
[email protected]Fax
Fax: 505-344-8646Fax
fax 212-320-0381Phone
(505) 934 2809Phone
212-320-0381Phone
212-971-1306Phone
505-344-8646Phone
505-401-4277Phone
505-884-0400Phone
917-414-7584Related Documents (6)
DOJ Data Set 10CorrespondenceUnknown
EFTA Document EFTA01765224
0p
DOJ Data Set 11OtherUnknown
EFTA02328489
1p
DOJ Data Set 10CorrespondenceUnknown
EFTA Document EFTA02125460
0p
DOJ Data Set 9OtherUnknown
From: "Jeffrey E." <[email protected]>
4p
DOJ Data Set 11OtherUnknown
EFTA02489202
1p
DOJ Data Set 10OtherUnknown
EFTA02086739
1p
Forum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.