61011
MAIN HOUSE POOL
ID
Task Name
Duration
Start
Finish
Predecessors
May
4/10
I
4117
I
4/24
5/1
I
5/8
I
5/15
j
5.22
1
Procurement
60 days
Mon 4/18/11
Frl 7/8/11 ifirrivrivintrivintrivrinivrivintrivintrivritrivrivintrivinivrivinivrivintrivinivrivinivrivintrivivrivirifirmanmannmannm
'
2
Site design
30 days
Mon 4/18/11
Fri 5/27/11
Lielgil ......
3
Pool file
32 days
Mon 41181 1
Mon elm 1
Mon 412vi 1
Mon 4,1/311
Mon 4,18,11
Mon 41611
Mon 4181 1
Mon 4x1811
Mon 4181 1
Tue 5/31/11
Fri 610111
Fri 5/27/1
Cr---
4
Site drains
40 days
5
Coral tie
30 days
._
100%
6
Site lighting
40 days
Fri 6/10/11
7
Rebar
15 days
Fri 5/6/11
Fri 4/22/11
Fri 718111
8
CMU
5 days
9
Doors/Frames/Shutters
60 days
.
10
Interior doors
60 days
Fri 7/8111
11
Punish hardware
60 days:
Fri 703/11
12
Root framing
45 days
Mon 4181 1
Fri 6.117/ 1
13
Roofing assembly
40 days
Mon 41811
Fri 61 0111
..,
14
Copper gutters
20 days
Mon 41811
Fri 513' 11 woo.
15
Shower enclosure
50 days
30 days
45 days
[repeated 4 times]
Mon 41811
Fri 6124111
Cr
r
16
Coral flooring
Mon 418/1
Fri 5/27/11
17
Vanity / Tops
Mon 418/1
Fri 6/17/11:
18
Plumbing fixtures
Mon 41811
Fri 6/17111
19
NC Systems
Mon 4,181 1
Fri 6/17111
20
Electrical fixtures
Mon 4/18111
Fri 617111
ar
21
22
105 days
23
Sltework
Mon 4/18/11
Fri 919111 giblIIIIIIIIIIIIIIIIIIIMMIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIMIII“
,.
24
Underground utilities
15 days
12 days
Mon 4/18/11
Fri 5611
3
25
100%
25
Pool tile
Wed 6/1/11
Thu 01611
Mon 7,411
Mon 7/411:26
26
Diamond Wile
12 days
Fri 6/17/11
27
Complete pool
0 days
Mon 7/4/11
28
Drainage
10 days
Mon 6/13/11
Fri 6124/114
29
Pool deck
20 days
20 days
30 days
5 days
5 days
10 days
Mon 6/27/11
Fri 7/22/1128
29F5-10 days
29F5-10 days
31
30
Coral tie
Mon 7/11/11
Fri 8/5/11
31
Stone walls
Mon 7/11/11
Fri 8/19/11
32
Finish grade
Mon 822/11
Fri 8/26/11
33
Landscaping
Mon 8,29111
Fri 912!1132
34
Site lighting
Mon 8 29111
Fri 9/9/1132
35
36
37
Cottage 64
147 days
Mon 4/18/11
Tue11/8/11 ret, r:::
.
-------- zI—tert
'in...in...L....L ,
%
38
Basement walls
15 days
Mon 4118111
Fri 5/6/11
39
Elevated slab
10 days
Mon 519111
Fri 5/20/11 38
,
-
.
,
w
100%
40
Waterproofing
2 days
Mon WW11
Tue 5/10/1138
Project: 1011 Updalel5Jull 1
Date: Mon 7/18/11
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
1
Project Summary ir;
External Tasks
O
External Milestone G
.
Deadline
.2.
unnuninuninnumussm
r
i
Ur
Page 1
EFTA01071350
#1011
MAIN HOUSE POOL
ID
Task Name
Duration
Sled
Finish
Predecessors
May
4/10
I
4117
I
4124
5/1
I
5/8
I
5(15
I
5/22
41
Foundation drain
2 days
Mon SIM
Tue 5/10/1138
Tolson-10096
a
0 100%
42
Cottage 114 backfil
3 days
Wed 5,11111
Fri5/13/1141
43
CMU
30 days
Mon &Ell
Fri 7/15/11 39FS+10 days
44
Root framing
10 days
Mon 711)1.11
Fri 7/29/11 43
45
Root assembly
20 days
Mon &1 ,'11
Fri 8/26/1144
46
Copper gutters
5 days
Mon 8,22,'11
Fn a2a€1145FS-5 days
47
Downspouts
2 days
Mon 8,29,11
Tue 8/30/1145
48
Stone veneer
30 days
Mon 8,15111
Fri 9/23/11 /45FS-10 days
49
Set door frames
3 days
Mon &29/11
Wed &31/1145 x.45
50
Interior framing
5 days
Mon 8,29(11
50
51
Interior plaster
15 days
Mon 9.,5111
Fri 923/11
52
Interior doors
5 days
Mon 9.,5,1 1
Fri 979/1150
53
Bathroom tile
5 days
Mon 926,11
Mon 10,31 1
Fri 9/30/1151
54
Shower enclosure
1 clay
Mon 10/3/1153
55
Vanity / Tops
2 clays
Mon 10.31 1
Tue 104'11
Mon 9,26,11
Mon 10.2111
Tue 10!4/1153
56
Accessories
2 clays
Wed 10/5/11 54
57
Interior painting
5 clays
Fri 9/30/1151
58
Flooring
5 clays
Fri 10/7/1157
59
Plumbing Rough
5 clays_
5 days
Mon 925111
Fri 919/1150
60
Plumbing Finish
Wed 10/5/11
Tue 10/11/1155
61
NC Systems
30 days
Mon 9/5/11
Fri 10/14/11 50
62
Electrical Rough
5 days
Mon 9/5/11
Fri 9/9/11 50
63
Electrical Finish
5 days Mon 10/10/11
Fri 10/14/11 58
64
Decorative Painting
10 clays Mon 10/17/11
Fri 10/28/1163
65
Punch List
3 clays Mon 10/31/11
Wed 11/211164
66
Clean up
2 clays
Thu 11/3/11
Fri 11 /4/11 65
67
Inspection
1 day
M01111/7/11
Mon 11/7/1166
68
Furnishings
1 day
Tue 11/8111
Tue 1118/1167
69
Completion
0 clays
Tue 11/8111
Tue 11 /8/11 68
Project: 1011 Update15Jul11
Date: Mon 7/18/11
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
-
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Project Summary
External Milestone
Deadline
0
.
unnuninuninnuniullum
G
V
Page 2
EFTA01071351
61011
MAIN HOUSE POOL
June
I July
I August
5122
I
5323
I
615
I
6/12
I
6119
I
6326
7/3
I
7/10
I
7/17
I
7/24
I
7/31
I
817
I
814
mm
,Izam,...„„mum 100%
....I l00%
low,
100%
•••••.-tee
-I fix%
• -, 100%
" 7:t
=
100%
. 100".
100%
100%
- 4 100% z 100%
--
Lua 100%
—.du 100%
:::zra 100%
c.
+
1 100%
i
c.
1'
+100k
.
7/4 in%
i
25%
*r
_
1Oo%
Baseline
[repeated 3 times]
Milestone
Summary
Summary
Project: 1011 Update15Jul11
Date: Mon 7/18/11
Critical
[repeated 3 times]
Task
Split
Task Progress
Split
Project Summary
External Tasks
External Milestone
Deadline
Split
Milestone O
•
Progress nautamaammuumuum
NT?
G
Progress
1
•
•
Page 3
EFTA01071352
#1011
MAIN HOUSE POOL
5/22
I
I June
5329
I
6/5
I
6/12
I
6119
I
6/26
I Jul)
I Arms(
7/3
I
7/10
I
7117
I
7/24
I
7/31
I
87
I
al4
Project: 1011 Update15Jul11
Date: Mon 7/18/11
Critical
Baseline
Project Summary
I•1
Critical Split
Baseline Split
External Tasks
Critical Progress
Baseline Milestone O
External Milestone G
Task
Milestone
.
Deadline
Split
Summary Progress ummumumuumumnuo
Task Progress
Summary
Page 4
EFTA01071353
01011
MAIN HOUSE POOL
I September
I October
I November
8121
I
8,28
I
9/0
I
9/11
I
9/18
I
9/25
I
10/2
I
10/9
I
10/16
I
loin
I
urao
I
11:6
I
11!13
.
53%
25:o
0%
Project: 1011 Updale15Jul11
Date: Mon 7/18/11
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Baseline
[repeated 3 times]
Milestone
Summary
Summary
Project Summary
External Milestone
Deadline
Split
Milestone O
•
Progress rummunmummumnum
V
G
G
•
Page 5
EFTA01071354
#1011
MAIN HOUSE POOL
I September
I October
I November
8/21
I
8/28
I
9/4
I
9/11
I
9118
I
9/25
I
10/2
I
10/9
I
10/16
I
10/23
I
10/30
I
1116
I
1 L13
'
*at 0%
0%
0%
.-93414=t ook
• 11
"a /8
)0%
0%
v
w
, 0%
7
0%
[repeated 5 times]
*
Project: 1011 Update15Jul11
Date: Mon 7/18111
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
L
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Project Summary
External Milestone
Deadline
7. 7-
G-
O
•
tunnunnumunnumunto
G
il
o
.i
.
Page 6
EFTA01071355
Technical Artifacts (2)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Phone
4118111Phone
6124111Forum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.