American Yacht Harbor
Facility Condition Status Report
September 2015
Addressing specific issues raised July 2015
-- I GY
MARINAS
EFTA01084560
Hurricane Shutters - Completed
Original pictures of the hurricane
shutters outside upper level office
Pictures of same, repaired and painted
in July/August 2015
,„--
EFTA01084561
Wall Paint - Completed
Original Pictures of exterior walls
around upper level office
6MINIIMMIONO-01,001°
6.
Pictures of same, repaired and painted
in July/August 2015
EFTA01084562
Dock beam repairs - Completed
Original picture of dock area near slip
Picture of same repaired September
B-26
2015
EFTA01084563
Main Flag - Completed
Original picture of flag with tattered
edge
Picture of same, replaced July 2015
EFTA01084564
Parking deck walls - Completed
Original pictures of lower parking deck
Pictures of same, repaired and painted
walls
July/August 2015
EFTA01084565
Parking Deck Columns - Completed
Original picture of column needing
paint
GARAGE PARKING
BEFORE 9AM WITi.
CURRENT PASS ON
LC)ITERIN
OLICITIK 9
Picture of same painted July 2015 — other
columns were painted as needed.
GARAGE PARKING
BEFORE 9AM WITH
CURRENT PASS ONLY
EFTA01084566
Dock planking — In-Progress
Original pictures (4 samples of many)
of various dock planking trouble spots
Sample pictures of recent and in-progress
dock repairs — September 2015
EFTA01084567
Security Fencing — In Progress
Original pictures showing fence
transition
Picture of same. As vegetation in this area
regrows, the fencing choice is more
understandable.
EFTA01084568
Piling wrap — In Progress
Original picture of pile with failing
wood wrap
Sample of a pile with completed wood
wrap. A project is underway to replace
failed wrapping on 24 concrete piles.
Expected completion in October 2015
EFTA01084569
Support columns — In Progress
Original pictures of support column
bases lifted off brick deck
Action Plan:
• Bases will be split open, lowered, and
reinstalled to be flush with brick deck
• Contractor quoted price approx. $75 per
columns
• 133 columns on B & C (Main) Building, for
total price of about $10,000
• Contractor is currently lowering 5 bases to
test feasibility
• If solution is workable, we will move forward
strategically to address most visible columns
first, and continue until aesthetics are
satisfactory
EFTA01084570
Parking Deck Ceiling — In Progress
Original pictures of damaged drop
ceiling in the lower parking deck
Action Plan:
• Materials are on order to begin replacement
of damaged ceiling tiles, support structure
and light fixtures.
• Drop ceiling near parking deck entrance is
being cut back to be flush and neat with
entranceway (areas shown in bottom to
picture on the left)
• The above efforts will lift aesthetics to
acceptable levels while we plan long term
solution
• Long term replacement or refurbishment
options are being explored and quoted for
completion in 2016
EFTA01084571
Elevator — In Progress
Original pictures of scraped paint on
the elevator doors
Action Plan:
• Doors have been repainted, but elevator use
for freight will continually scrape paint
• Elevator doors and trim areas are being fitted
with stainless steel rub rails/guards to protect
paint while remaining aesthetically pleasing
• Interior of elevator cab is also being
refurbished, including polishing of stainless
steel, new paint and new flooring.
• Completion expected in Q4 2015
EFTA01084572
Brick Pavers — In Progress
Original pictures of various areas of the
brick paver deck needing attention
Action Plan:
• Brick paint is being color custom color
matched to better blend repair areas with
original brick.
• Patch and replacement bricks are installed
where need.
• Long term resurfacing or repainting option
are being explored by local contractors. Two
primary options are 1) Coating with a heavy
duty masonry paint or 2) removal and
replacement of entire system of brick pavers
• Either option above will be a significant
undertaking, expected to start and complete
project in 2016
EFTA01084573
Stairways — In Progress
Original pictures of stairways
Action Plan:
• Local structural engineer Paul Ferreras, PE has
inspected the property's stairways and written a
letter recommending refurbishment over
replacement
• Two local welding contractors are producing job
quotes to address all structural steel issues with
stairways
• Concrete stair treads will be painted to match
paver bricks on surrounding decks
• Steel will be repainted black after above repairs
are complete
• All repairs expected to be completed in Q4 2015
EFTA01084574
P Dock — In Progress
Original pictures of areas around
P-Dock
Action plan:
• P-Dock is owned by 3rd party and slips are
managed by AYH
• Dock owner is refurbishing entire dock
structure and utilities starting October 2015
• AYH/IGY management team working with P-
Dock owner to ensure rebuilt dock meets
safety and aesthetics standard.
• Expected completion January 2016.
EFTA01084575
Technical Artifacts (3)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Wire Ref
refurbishedWire Ref
refurbishingWire Ref
refurbishmentForum Discussions