LSJ CONSTRUCTION
Subcontractor Payout
Project:
Flagpole Pool #1013
Trade:
Pools
Subcontractor Virgin Islands Gunite Pools
nvoice #
Phase #
Requisition #6
13-150
Original Contract Sum:
Change Orders Submitted & Approved:
New Change Orders:
Total Work Contracted to Date:
September 26, 2011
Insurance ex iration: Ma 14, 2012
Partial
X
Requisition #6
Final
$200,000.00
$25,213.44
$0.00
$225,213.44
Total Work Completed to Date:
93%
$210,471.25
Less Retainage:
Total Payments Made to Date:
Total Current Payment Due:
Balance to Finish including Retainage:
Sales Tax Liability:
a. Subcontractor/Supplier is liable, explaii Labor and materials
b. Non-resident Subcontractor/Supplier Bond Applicable:
c. Use Tax to be paid by our company:
d. Shipping
$0.00
$170,471.25
$40,000.00
$14,742.19
incl.
Total Outlays for this contract incl. Sales or Use Tax:
$210,471.25
,V)
JEE approval attached
YES
NO
X
Submitted Bill
Signed:
Date: September 26, 2011
Approved by: Emad
Signed:
Invoice Attached
YES
NO
Approved by: Gary
Signed:
Da : September 26, 2011
Approved/by:
Signed:
EFTA01123619
LSJ CONSTRUCTION
Project Flagpole Pool #1013
:ontractor - full legal name: Virgin Islands Gunite Pools
Phase # 13-150
Trade: Pools
Invoice #: Requisition #6
Insurance expiration: 5/14112
Payment
Partial
Final
X
Invoice/Reg#
Date
C/O
Amount
Retainage
Due
Paid
Date Paid
Check#
Balance
Contract
02/02/11 Pool
200.000.00
CON1
CO#2
CO#3
CO*4
CO#5
06/29/11 Change plaster
10.471.25
09/06/11 upgrade board
9017.75
09/06/11 Lighting
1460.44
09/06/11 Cartridges
2.264.00
Requisition #1
Requisition #2
Requisition #3
Requisition #4
Requisition #5
Requisition #6
02/15/11 Deposit
40.000.00
0.00
40000.00
40000.00
0.00
03/02/11 Steel Complete
40,000.00
0.00
40.000.00
40000.00
0.00
03/22/11 Gunite Complete
40,000.00
0.00
4000000
40.00000
0.00
06/10/11 Tile Complete
40.000.00
0.00
40.000.00
40.00000
000
07/11/11 Change plaster
10.471.25
0.00
10,471.25
10.471.25
0.00
09/06/11 Progress
40.000.00
0.00
40.000.00
40.000.00
Total
210.471.25
0.00
210,471.25
170471.25
40.000.00
Date Revised:
September 26, 2011
Contract Amount - Phase
contract
CO#1
CO#2
CO#3
CO#4
CO#5
Pool
Change plaster CO5
upgrade board
Lighting
Cartridges
200.000.00
10.471 25
9.017 75
3.460 44
2.264 00
Contracted To Date
Balance of Contract w/Retainage
225.213.44
14.742.19
EFTA01123620
Lake Havasu Gunite and Concrete/Virgin Island Gunite Pools
„
I r '
BILL TO
cle13O1 lop 'Nunn/. and whom %%ill. your payment
Invoice
DATE
INVOICE #
‘)
2t)I I
1011
TERMS
DUE DATE
Net 30
10/06/201 1
AMOUNT DUE
ENCLOSED
560,206.19
chi- -wig
Activity
Amount
• Final balance due upon start-up and use
• Change order #3 - Upgrade to 14 11. diving board
• Change order #8 - &-12V lights
• Addition • 6 LED pool lights, controllers, and transformers
• Addition - 16 new cartridges for clean and clear 520 sq. ft. filters
• Manifold bottom/pipe assembly - bulk head unions, O rings and labor to repair pool equipment caused by dead
heading equipment
Project: Flagpole Pool #1013
ri llenTfr
110000
-FSku
Vir,q4 ‘ .
40,000.00
9,017.75
3,460.44
5,461.00-
'
2,264.00
0.00
owl
,
EFTA01123621
Technical Artifacts (1)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Phone
4000000Forum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.