Zorro Projects - 5/31/13
Landscaping (22) -
Rear Planter Bed
Front & Rear Parking Beds
Bowel Garden
Aspen Grove
Pinion Screen
Start
End
Total Est. Cost
6/1/13
Notes
$75,000.00
3/28/13 - Refurbishment & Maintenance proposals from 3
companies forwarded to RK & DI
4/27/13 - JE approved Aspen Landscaping for Refurbishment
5/9/13 - New proposal forwarded to JE & RK, awaiting direction
5/16/13 - Final proposal forwarded to RK, will discuss with JE
5/24/13 - Aspen agreed to $75,000
5/31/13 - $44,383.08 Deposit issued to Aspen
Landscape Lighting Timers Replacement-
Start
End
Total Est. Cost
$5,000.00
Notes
Photo
4/27/13 - JE approved
5/1/13 - Unable to move forward until Project 22 - Landscaping
has been resolved
6/1/13 - Brice to review with Aspen about location etc.
Landscaping - in House -
Ponderosa Pines & Landscape Ughts at
Front Entrance
Terraces (27) -
Terraces - $52,000.00
Stucco/Gutters/Painting - $4,200.00
4/7/13
Start
End
Total Est. Cost
Notes
-4
Start
End
Total Est. Cost
$56,200.00
Photo
4/27/13 - JE approved the removal of existing Ponderosa Pines,
Landscape Lights & to relocate Pinions to the area.
Removal of Dead Pine in Front Courtyard.
REQUIRE APPROVAL TO PROCEED WITH REMOVAL
Notes
12/12/12 - Bid Received
3/20/13 - JE approved
4/20/13 - library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
5/31/13 - There was a fault in one of the rolls of material, vendor
has reordered, will recover area once on site.
6/3/13 - Start gutter & stucco work
6/10/13 - Project completion expected
EFTA01124612
Zorro Projects - 5/31/13
Front Gates Openers Call Boxes (30) -
Start
End
Total Est. Cost
Notes
4/20/13 - Bid received, have requested vendor to make
adjustments
5/9/13 - Received revised bid. Options & Equipment reviewed
5/12/13 - Options & Equipment selected, final bid due 5/21/13
5/21/13 - Final bid received via fax, unable to read, vendor will
resend.
Cooling Tower -
6/1/13 - Final bid expected
Start
End
Total Est. Cost
Notes
4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded, awaiting confirmation
6/17/13 - Due to ship to ZDC
Replacement of Pool Pae (33)
-
Engineering Inspection - $9,100.00
Unit Cost - $43,170.00
Ducting - TBA
Repair Pool/Spa (29) -
Water Sample of Tap Water -
Start
End
Total Est. Cost
9/11/12
Notes
4/29/13 - Quote forwarded to RK, who requested more detail
5/8/13 - Revised quote forwarded to RK, awaiting direction
5/22/13 - Beaudin Ganze on site to review project
5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera. JBH have been
approached for estimate
Start
End
Total Est. Cost
Notes
$12,600.00
15/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
JE requested work be completed in Sept
REQUIRE CONFIRMATION THAT BID IS ACCEPTED, SO VENDOR
CAN BE PLACED INTO SCHEDULE
Start
End
Total Est. Cost
Notes
4/27/13 - JE requested water samples be taken.
will be completed once water system is balanced
5/10/13 - Dakota RO is down, pressure issues
6/5/13 - Water samples to be taken
This
Photo
Photo
Photo
Photo
Photo
EFTA01124613
Zorro Projects - 5/31/13
Exterior Doors Main House -
Start
End
Total Est. Cost ,
Notes
Photo
Total Est. Cost
4/27/13 - JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
il
.Terraces etc. complete
Audio Upgrade -
Start
End
Notes
Photo
New N's
DVD Players/Theater Upgrade
Installed - final programming required
Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before moving
forward
5/24/13 - Receiver on site
- Work to begin
_16/3/13
I
Kitchen Table Electrical -
Start
End
Total Est. Cost
Notes
Photo
Electrical & Data Cut In - $2,160.00
3/1/13 - Bid received Lead Time 1 Week
Need to review design and floor
End
Media Room Curtains (24) -
Start
Total Est. Cost
Notes
Photo
Blackout & Rings
2/24/13
$6,262.08
4/27/13 - JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Sarah's Office Curtains (25) -
Start
End
Total Est. Cost
Notes
Photo
Lined & Rings
2/24/13
$2,527.01
4/27/13 - JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yardage
of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Gym - Mirrored Doors - Backed/Framed
Start
End
Total Est. Cost
Notes
Photo
2/24/13
3 B's completed, JE requested further work, will review with
vendor
EFTA01124614
Zorro Projects - 5/31/13
Phones Main House (31) -
Start
End
Total Est. Cost
Notes
Photo
534,295.00
4/27/13 -JE approved installation of new phones at MH
5/14/13 - Awaiting engineered solution for delivery of services
(phone/data) before proceeding
Start
End
Microwave & IT- (21)-
Total Est. Cost
Notes
Photo
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 -JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded details of RSM Craig
Franck. Brice has been in contact with Craig will forward details
5/24/13 - Received bid from Southwestern Wireless, have call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK & JR
Cell Repeaters & Wi-Fl
Start
End
Total Est. Cost
Notes
Photo
Cell Repeater - Library
Will have installed by 5/17/13
Cell Repeater - Gym
Will be completed with Audio install
Computers,-
Start
End
Total Est. Cost
Notes
Photo
Lap Top - Lodge
Requesting Approval to Purchase
Desk Top - RC Office
Requesting Approval to Purchase
Well K (20) -
Start
End
Total Est. Cost
Notes
Photo
Plugging First Hole
Multi Media Filters & Install
Mis Pipe & Fittings
4/27/13 5/31/13
$15,000.00
$5,844.57
$822.20
4/27/13 -JE approved
5/3/13 - Multi Media Filters ordered
5/17/17 - Pipe & Fitting due on site
5/28/13 - Multi Media Fitters to installed
5/31/13 - Project Complete
EFTA01124615
Zorro Projects - 5/31/13
Dakota RO Water Softener
Start
End
Total Est. Cost
Notes
Photo
2/18/13 5/31/13
$3,045.45
5/3/13 - Well & RO on line
5/10/13 - Dakota RO off Line, pressure issues - recalibration due
5/20/13 - Water Softener Installed
5/24/13 - Clock on Water Softener, needs to be replaced. Dakota
on line but requires manual operation, requiring 2 hours.
5/28/13 - Clock replaced
5/31/13 - Project Complete
Lo
_til
Start
End
Total Est. Cost
Notes
Roof - Repair/Replace Broken Sections
Start
Three 8% will complete while on site for upcoming projects
Log Cabin
End
Total Est. Cost
Notes
Photo
Step Outside - Repair/Replace
2/24/13
Start
NA
End
Caboose
Total Est. Cost
Photo
Outside Wall - Installation of Retaining Wall
End
NA
Yurt (23) -
Start
Total Est. Cost
Notes
Photo
Replacement Walls/Roof/Door/Windows
5/9/13
$6,355.00
plus shipping
charges of
approx.
$480.00
4/27/13 - JE approved Investigating options
5/9/13 - Project Request forwarded to RK & JE
5/9/13 - JE approved Project, awaiting direction on deposit
payment from RK
5/13/13 - Deposit forwarded to vendor $3,177.50
6/24/13 - Removal of furniture, deconstruction of existing
walls/roof/windows & door to begin. Then reconstruction of base, j
resanding/sealing floor required - in house
7/3/13 - Scheduled Ship Date
End
Refurbishment Yards/Grass Areas RC (32)
Start
Total Est. Cost
Notes
Photo
Due to poor preparation & selection of soil
In 2012 all yards/grass areas need to be
refurbished
5/16/13 5/31/13
5/16/13 - Tilling & Manure/Soil installation started in Red &
Yellow yards
5/24/13 - Seed on site, work continues
5/30/13 - All seed installed, irrigation installation complete
5/31/13 - Project Complete
EFTA01124616
Zorro Projects - 5/31/13
Painting/Staining/sealing -
Start
End
Total Est. Cost
Notes
Photo
Hay Barn
5/13/13
90%- Staining of trim to be completed
5/30/13 - Work to start, due to high winds work to begin 6/10/13
Bunkhouse
4/14/13
80% - Staining of trim & deck to be completed
5/30/13 - Work to start, due to high winds work to begin 6/10/13
Bay Garages
5/13/13
90% - Staining of trim to be completed
5/30/13 - Work to start, due to high winds work to begin 6/10/13
Fire House - including outside lights
5/28/13 - Work to begin, due to high winds work to begin 6/6/13
Stables
5/29/13 - Work to begin, due to high winds work to begin 6/6/13
Log Cabin
Work to begin once all painting/staining projects complete at RC
Lodge
Work to begin once all painting/staining projects complete at RC
Reservoir
Work be begin once all painting/staining/sealing projects complete
Repair/Painting Work - Ion (34)-
Start
End
Total Est. Cost
Notes
Start
5/17/13 - E Mail/Photos forwarded to JE showing work
5/23/13 - Forwarded details to Ion, including work that will be
required after Master Terrace ceiling is repaired
Bunkhouse
End
Total Est. Cost
Notes
Window/Doors - Total Replacement
2/6/121—
Will Budget for 2014
End
Cactus Removal
Start
Total Est. Cost
Notes
Removal of Cactus to begin late Fall, early Winter
End
Total Est. Cost
Vehicles
Start
Notes
2013 Ford Expedition - review Captain
Seats to be installed
3/27/13
5/2/13 - Estimate received - $11,528.74
5/31/13 - as of date unable to get a 2nd estimate,
EFTA01124617
Zorro Projects - 5/31/13
Start
End
Total Est. Cost
Notes
14/27/13 -JE approved investigating purchase of 2 dogs.
Researching
Purchases
White Rug & Pad (26) - Gym (10 x 12)
Start
End
Total Est. Cost
4/27/13
4/27/13 - JE approved Robert's to manufacture a rug using carpet 1-
used in
Office. Vendor no longer stocks this brand, will add
10% for special order.
5/15/13 - 2 Estimates received
5/16/13 - Estimate forwarded to JE - Enchantment Carpet
5/16/13 - Project approved
$862.55
6/5/13 - Rug due on site
Big Urns - Outside MH
Outside Pool Furniture
Pool Pace Clock
Large Chrome Pool Clock
Facial Machine
4/27/13 -JE approved Terre Cotto constructed Urns
6/5/13 - Will forward possible options
4/25/13 - Ordered, lead time 4 to 5 weeks
nvestigating options
o purchase
EFTA01124618
Technical Artifacts (3)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Wire Ref
RefurbishmentWire Ref
referenceWire Ref
refurbishedForum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.