Master Suite Budget Cover sheet
June 5 , 2009
Jeffrey:
General Conditions
Inspections/Testing
Survey
Demolition
Shoring
Pest Control
Concrete
Masonry
Metals
Wood Framing
Architectural wood work
Roof
Doors and Windows
Finishes
Specialties
Steam Room Equipment
Plumbing
HVAC
Electrical
Sub Total
Contingency, 5%
Total
$18,300.00
$9,500.00
$3,500.00
$15,540.00 Based on using rock and concrete as backfill on other projects
$6,400.00
$2,260.00
$25,028.00 LJS labor only
$33,801.00 LJS labor only
$10,820.00
$105,350.00 Plan shows metal patern railing - WOOD used
$18,450.00
$84,744.00 GENSLER Specification not included -
$88,068.00
$50,776.00
$15,738.00 All items self specified in back up
$7,615.00 Self specified Steamist system 30
$32,280.00 LSJ performed work with Subcontract sign off - fixtures self specified in back t
GENSLER Specification not included - includes all new systems & air
542,798.00 cleaner - Self Specification Listed in backup
$21,534.50 LSJ performed work with Subcontract sign off self specified
$592,502.50
$29,625.13
$622,127.63
On the attached pages is a more detailed breakdown of trade items
1. LSJ performed construction is in Brown
2. Subcontractor performed work is in Blue
3. Totals are in grey
Curtis
EFTA00731169
Master Suite Budget Cover sheet
EFTA00731170
Forum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.