JE Punch List —August 28, 2012 Directive Updates

Date
Unknown
Source
DOJ Data Set 9
Reference
efta-efta01107272
Pages
3
Persons
0
Integrity
No Hash Available

Summary

Ask AI About This Document

0Share
PostReddit

Extracted Text (OCR)

EFTA Disclosure
Text extracted via OCR from the original document. May contain errors from the scanning process.
JE Punch List —August 28, 2012 Directive Updates 1. Clean Up - make as many barge runs as necessary 2. Equipment and Vehicles - Sell equipment - Non-working ATVs and gators will be off island by 8/29 - No machinery off the island unless approved - (4) 2012 Kawasaki 750 EPS, (2) 2012 Kawasaki Mule 4010, parts, and 1 of 3 Queen seats on LSJ 8/28 - New seats for gators and pro gators — ordered by 8/31 3. Computers - Per JE, refurbish old units —Jermaine - PC from NYC to Carlos — Marine —Jermaine received 8/28 to wipe - 25 inch I Mac from NYC— Captains Office 4. Five Palms - Internet/Phone Switch installation — final stage to be completed - Jermaine 8/30 - Exterior Door Shutters — ordered — awaiting completion date from vendor - Painting - outside to be completed via JE direction - Furniture — outside furniture in place — Karen to tie down cushions to resolve wind issues - Picture Frame — measurements forwarded to Sarah - 86 x 70 - Mirrored siding — section that flew off in storm has been reglued - Transformer Protection Shelter — walls complete, primer complete, concrete fill in progress, reviewing options/expense for roof, forward by 8/30 - Fire pit — repairs completed 5. Grotto - Curtains — installed - Mattress cover — unable to purchase cover without mattress — suggest buying fabric, making cover locally - Genset wiring — COMPLETE — Electronic Remote Starter, auto start from Kite House, ordered 8/10. Danny follow up - Desk — needs repair — completion 8/31 6. Berm/Top of Hill - Hydroseed inside — complete - Hydroseed outside — will need to review progress - Palm inside — damaged — will review viability - Top of hill — outside of berm to be hydroseeded 7. Engineering/Maintenance Yard - Engineering Bays — drainage complete — epoxy completed 8/28 8. Triangle - - Must design triangle — awaiting JE direction 9. Flagpole Pool Cabana - - Furniture — desk from Paris ready to ship early September - Sue - No cold water in the bathroom sink — reviewing replacing the faucet - Hydroseed pull box - Trim palms - complete 10. Floating Dock - Jet ski bumpers — complete — reviewing whether this type resolves the issues with the jet skis - Table/Dock Box - Dock box top to be revarnished — Carlos has a possible solution check out tables - Swim Ladder — direction from JE on placement required - Dive Platform — require construction details 11. Entry Tree Lights — JE approved photocell timer — installation COMPLETE 12. Solutions for Generators EFTA01107272 — Soundproofing Installed — COMPLETE 13. Tiki — Shields — sealed — COMPLETE - review installation process 14. Chillax Room — requires furniture piece for electrical/media equipment — Sarah 15. Chillax Bathroom - require blue rugs for bathroom & vanity area — Sarah 16. Mechanical Building Transformer —on route to Tropical FL 17. Boats - Lady G — sell — in hurricane storage 7/18 - Lady K — sell — survey forwarded to Darren & Rich, suggested price $225,000 - Big N — repair — at Subbase — work begins 8/28 - Little C — engine at Offshore 8/29 — installation complete by 9/4 18. Timers - Review installing timers on air conditioners, irrigation water systems, and lights - Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas — they remain at 85 degrees - Irrigation — depending on rainfall 19. Beach lighting — per JE, replace existing transformers for the beach lighting of palms around the salt pond and beach 20. Transient Surge Protection — estimate will be forwarded by 8/31 21. Ice Maker — installation complete 22. Landscaping - Pop's Garden — need deer fencing, or some other method of protection - Dead palms — all to be removed - Cut grass, acacia — owner's drive, blue beach, stone walls, gym - Garbage dump — hydroseed - COMPLETE 23. Solar lights — place every 30 feet — work in progress 24. Roads - - Priority is Gym road grading — Jules - Jules to line the service road with boulders — COMPLETE 25. Library - Lights on bookshelves need attention — Danny will start ASAP 26. New Employee Bathrooms 27. Gym - New punching bag — on site — installation after JE visit - Subwoofer — torn or blown — Scott to research a replacement speaker — photos and information sent 8/3 - Clean gutters — COMPLETE - Windows in the ballet room need repair to both cranks and panes — Karen to review 28. Beach Office - complete electrical overall required - waterproofing/sealing/painting/replace rotten wood required 29. LSJ Mooring — Darren forwarded to Army Corp for final approval — awaiting response 30. Hangar - Fuel Containment Pad — draft approved with drainage incorporated, waiting for updated plan 31. Main compound - Wind doors to the east are inoperable — blew off on Friday — will review more permanent repairs - Lights — Danny has a complete list of lights which are not on, etc — will review PM 8/28 thru the night until complete Acid Washing of lanterns — completed by 8/31 32. New waste bins — (2) 20 yard bins on LSJ 8/28 32. Yellow Nap House — to be demolished — by 9/30 33. Blue Nap House — replace and repair shingles EFTA01107273 EFTA01107274

Technical Artifacts (1)

View in Artifacts Browser

Email addresses, URLs, phone numbers, and other technical indicators extracted from this document.

Wire Refrefurbish

Forum Discussions

This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.

Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.