Zorro Projects - 6/22/13
landscaping (22) -
Rear Planter Bed
Front & Rear Parking Beds
Bowel Garden
Aspen Grove
Pinion Screen
Start
End
Total Est. Cost
Notes
6/1/13
$75,000.00
3/28/13 - Refurbishment & Maintenance proposals from 3
companies forwarded to RK & DI
4/27/13 -JE approved Aspen Landscaping for Refurbishment
5/9/13 - New proposal forwarded to JE & RK, awaiting direction
5/16/13 - Final proposal forwarded to RK, will discuss with JE
5/24/13 - Aspen agreed to $75,000
5/31/13 - $44,383.08 Deposit issued to Aspen
6/1/13 - Project Started
6/8/13 - Work continues, soil preparation in progress
6/14/13 - Plant material starting to arrive, more due next week
6/18/13 - More plant material arrived
6/21/13 - Planting & Irrigation complete at back parking area.
6/22/13 - Planting & Irrigation continues around chess set -
attached photos
Landscape Lighting Timers Replacement -
Start
End
Total Est. Cost
Notes
$5,000.00
4/27/13 - JE approved
5/1/13 - Unable to move forward until Project 22 - Landscaping
f has been resolved
6/1/13 - Brice to review with Aspen about location etc.
6/7/13 - Awaiting electrical proposal from RMC Electric due
6/24/13
Landscaping - In House -
Start
Ponderosa Pines & Landscape Lights at
6/3/13
Front Entrance
Total Est. Cost
Notes
4/27/13 - JE approved the removal of dead pine in courtyard &
Ponderosa Pines, Landscape Lights & relocate Pinions to the area.
6/3/13 - Project Started
6/7/13 - Removal of Ponderosa Pines complete
6/18/13 - Removal of courtyard Pine complete
6/25/13 - Work to begin on landscape lighting
Photo
X
Photo
Photo
EFTA01124648
Zorro Projects - 6/22/13
Terraces (27) - Three B's
Start
End
Total Est. Cost
Notes
Terraces - 552,000.00
4/7/13
$56,200.00
12/12/12 - Bid Received
Stucco/Gutters/Painting - $4,200.00
3/20/13 - JE approved
4/7/13 - Project Started
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
5/31/13 - There was a fault in one of the rolls of material, vendor
has reordered, will recover area once on site.
6/7/13 - Material on site, will continue 6/10/13
6/14/13 - Membranes & Gutters Complete - attached photos
6/18/13 - Stucco & Painting scheduled to start
6/21/13 - Stucco & Painting Complete - attached photos
6/24/13 - Final review of completed work
Front Gates Openers Call Boxes (30) -
Start
End
Total Est. Cost
Notes
4/20/13 - Bid received, requested vendor to make adjustments
5/9/13 - Received revised bid. Options & Equipment reviewed
5/12/13 - Options & Equipment selected, final bid due 5/21/13
5/21/13 - Final bid received via fax, unable to read, vendor will
resend.
6/8/13 - Final bid attached, also forwarded separately to RK.
6/11/13 - RK requested material breakdown
6/14/13 - Material breakdown forwarded to RK
6/19/13 - Resubmitted revised pricing to RK - awaiting direction
Cooling Tower (36) - JBH
Start
End
Total Est. Cost
Notes
4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded, awaiting confirmation
6/20/13 - Unit on site - attached photo
6/21/13 - Noting attached E Mail, JBH have pulled their team off
moving forward with this project until RK makes contact about
outstanding balance
Photo
x
.Photo
Photo
EFTA01124649
Zorro Projects - 6/22/13
Replacement of Pool Pac (33) -
Start
End
Total Est. Cost
Notes
Photo
.
_
Engineering Inspection - $9,100.00
9/11/12
4/29/13 - Quote forwarded to RK, who requested more detail
Unit Cost - $43,170.00
5/8/13 - Revised quote forwarded to RK, awaiting direction
Camera Ducting Inspection - $1,214.91
5/22/13 - Beaudin Ganze on site to review project
Ducting - TBA
5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera.
6/3/13 - JBH forwarded estimate
6/4/13 -JE approved moving ahead
6/11/13 -JBH due on site
6/12/13 - JBH on site, completed camera inspection, awaiting
report/disc.
6/21/13 - Report/Disc forwarded to Beaudin Ganze, awaiting
review
.
.
Repair Pool/Spa (29) -
Start
End
Total Est. Cost
Notes
Photo
$12,600.00
Water Sample of Tap Water -
Start
End
Total Est. Cost
5/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
JE requested work be completed in Sept
Photo
Notes
6/12/13
.
Exterior Doors Main House - Three B's
Start
,
4/27/13 - JE requested water samples be taken.
This will be completed once water system is balanced
5/10/13 - Dakota RO is down, pressure issues
6/2/13 - All Wells up and running
6/12/13 - Water samples taken. Results due back 6/24/13
.
Notes
Photo
End
Total Est. Cost
4/27/13 - JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
EFTA01124650
Zorro Projects - 6/22/13
Audio Upgrade - In House
Start
End
Total Est. Cost
Notes
New TV's
6/3/13
Installed - final programming required
DVD Players/Theater Upgrade
Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before moving
forward
5/24/13 - Receiver on site
6/3/13 - Work to begin
6/7/13 - Work 80% complete in Gym, Breakfast Rm, Lodge & BH
6/12/13 - Gym, Lodge & BH Systems Complete
6/14/13 - Will exchange the Samsung DVD for a Marantz DVD in
Breakfast Rm
6/22/13 - Awaiting delivery of Marantz DVD
Photo
Kitchen Table Electrical - (35) -Three B's
Start
End
Total Est. Cost
Notes
Photo
Electrical & Data Cut In - $2,160.00
6/3/13 6/13/13
3/1/13 - Bid received Lead lime 1 Week
6/3/13 - Project Started
6/7/13 - Under floor conduit due to be completed 6/12/13
6/13/13 - Conduit installed, tiles replaced & grouted. Cat 5 still to
be pulled and punched down
Media Room Curtains (24) -
Start
End
Total Est. Cost
Notes
Photo
Blackout & Rings
2/24/13
$6,262.08
4/27/13 - JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Sarah's Office Curtains (25) -
Lined & Rings
Start
End
Total Est. Cost
Notes
Photo
2/24/13
I
$2,527.01
4/27/13 - JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yardage
of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
EFTA01124651
Zorro Projects - 6/22/13
Gym - Mirrored Doors - Three B;s
Start
End
Total Est. Cost
Notes
Photo
2/24/13',
3/4/13 - Project Complete. JE requested further work, which will
begin once Project 27 - Terraces complete
End
1
Phones Main House (31) -
Start
Total Est. Cost
Notes
Photo
4/27/13 - JE approved installation of new phones at MH
Awaiting for service provision & estimated cost of delivery of
services - Project 21 Microwave & IT
6/22/13 - Awaiting response from Southwestern Wireless on FCC
License Application & Router at MH
Start
End
Phones Ranch Central (351-
Total Est. Cost
Notes
Photo
6/21/13 - Will forward proposal for phone system by 6/28/13
Photo
MIcrowaveALT - (21) -
Start
End
Total En. Cost
Notes
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 - JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded details of RSM Craig
Franck. Brice has been in contact with Craig will forward details
5/24/13 - Received bid from Southwestern Wireless, have call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK & JR
6/8/13 - Forwarded TW Telecom Proposal for Delivery of Services
to JE & RK. Firm Bids due by 6/14/13
6/14/13 - Received bid from Southwestern Wireless, confirming
details before forwarding
6/15/13 - Informed JE, will forward once all details confirmed
6/20/13 - JE approved South Western Wireless bid. RK to
negotiate final bid
EFTA01124652
Zorro Projects - 6/22/13
Cell Repeaters & Wi-Fi - In House
Start
End
Total Est. Cost
Notes
Photo
Cell Repeater - Library
_
Will have installed 6/28/13
Cell Repeater - Gym
Will have installed 6/28/13
Total Est. Cost
Computers -
Start
End
Notes
Photo
Lap Top - Lodge
_
Requesting Approval to Purchase
Desk Top - RC Office
Requesting Approval to Purchase
Well K (37) -
Start
End
Total Est. Cost
Notes
Photo
Plugging First Hole
$15,000.00
Estimate to plug 1st hole
Lod e Roof
Start
4
Total Est. Cost
Notes
Photo
Repair/Replace Broken Sections
_
Three B's will complete while on site for upcoming projects
Start
Yurt - (23) -
End
Total En. Cost
Notes
Photo
Replacement Walls/Roof/Door/Windows
5/9/13
$6,355.00
plus shipping
charges of
approx.
$480.00
4/27/13 -JE approved investigating options
5/9/13 - Project Request forwarded to RK & JE
5/9/13 - JE approved Project, awaiting direction on deposit
payment from RK
5/13/13 - Deposit forwarded to vendor $3,177.50
6/24/13 - Removal of furniture, deconstruction of existing
walls/roof/windows & door to begin. Then reconstruction of base,
resanding/sealing floor required - in house
7/3/13 - Scheduled Ship Date
Repair/Painting Work-Ion
Start
End
Total Est. Cost
Notes
Photo
5/7/13 - E Mailed Photos to JE showing work required
5/23/13 - Forwarded all work details to Ion, including work that
will be required after MBR Terrace is completed
EFTA01124653
Zorro Projects - 6/22/13
(
Painting/Staining/Sealing - In House
Start
End
Total Est. Cost
Notes
Photo
Stables - including outside/Inside lights
6/27/13 - - Work to begin
Adobe - Including wooden deck & front
Work to begin once stables complete
Log Cabin
Work to begin once all painting/staining projects complete at RC
Lodge
Work to begin once all painting/staining projects complete at RC
Reservoir
Work be begin once all painting/staining/sealing projects complete
Fuel Storage Tanks
Work to begin once all painting/staining/sealing projects complete
RC Office Interior
Work scheduled for Winter
RC Mechanical Bays - Interiors
Work scheduled for Winter
RC Garages - interiors
Work scheduled for Winter
Fuel Storage Tank Area - In House
Start
End
Total Est. Cost
Notes
Photo
Removal of grass. Matting & edging to be
installed
Gravel/Edge Work RC Paths - In House
Start
End
Total Est. Cost
Notes
Photo
All paths to be dug out, edged and gravel
to be installed
Log Cabin - In House
Start
End
Total Est. Cost
Notes
Photo
Step Outside - Repair/Replace Broken
Section
Caboose - In House
Start
End
Total Est. Cost
Notes
Photo
Installation of Retaining Wall
EFTA01124654
Zorro Projects - 6/22/13
4 Bay Garages - In House
Start
End
Total Est. Cost
Notes
Repair Leaking Roof
Repair Damaged Wall
Pole Barn Water Truck Parking
Start
End
Total Est. Cost
Notes
Photo
Installation of a Retaining Wall
To begin late Fall, Early winter
Cactus Removal - In House
Start
End
Total Est. Cost
Notes
Ph
oto
Removal of Cactus to begin late Fall, early Winter
Vehicles
Start
End
Total Est. Cost
Notes
Photo
2013 Ford Expedition - review Captain
Seats to be installed
3/27/13
5/2/13 - Estimate received - $11,528.74
5/31/13 - as of date unable to get a 2nd estimate,
ft E
Start
End
Total Est. Cost
Notes
Photo
4/27/13 -JE approved investigating purchase of 2 dogs.
Researching
Inventory/Clean Work Shops - In House
Start
End
Total Est. Cost
Notes
Photo
6/6/13
6/20/13 - Landscaping, Paint & Wash Bay 90% complete -
attached photos. All these location will be painted over the winter
6/21/13 - Work continues as time allows - complete dean up &
inventory of all work shops at RC & MH
Start
End
Total Est. Cost
Purchases
Notes
Photo
Big Ums - Outside MH
4/27/13 - JE approved Terre Cotto constructed Urns
Outside Pool Furniture
Investigating Options
Pool Pace Clock
4/25/13 - Ordered, lead time 4 to 5 weeks. Trying to track this down
large Chrome Pool Clock
Investigating Options
Facial Machine
o purchase
Wells - Dakota & K
Combined Usage as of date 6/14/13
6.86 afa
EFTA01124655
Zorro Projects - 6/22/13
2014 Budget
I
Bunkhouse
Bag
End
Total Est. Cost
Photo
Window/Doors - Total Replacement
EFTA01124656
Technical Artifacts (2)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Wire Ref
RefurbishmentWire Ref
referenceForum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.