Zorro Projects - 6/29/13
Landscaping (22) -
Start
End
Total Est. Cost
Notes
Photo
Rear Planter Bed
Front & Rear Parking Beds
Bowel Garden
Aspen Grove
Pinion Screen
landscape Lighting Timers Replacement -
6/1/13
Start
End
$75,000.00
3/28/13 - Refurbishment & Maintenance proposals from 3
companies forwarded to RK & DI
4/27/13 - JE approved Aspen Landscaping for Refurbishment
15/9/13 - New proposal forwarded to JE & RK, awaiting direction
5/16/13 - Final proposal forwarded to RK, will discuss with JE
5/24/13 - Aspen agreed to $75,000
5/31/13 - $44,383.08 Deposit issued to Aspen
6/1/13 - Project Started
6/8/13 - Work continues, soil preparation in progress
6/14/13 - Plant material starting to arrive, more due next week
6/18/13 - More plant material arrived
6/21/13 - Planting & Irrigation complete at back parking area.
6/22/13 - Planting & Irrigation continues around chess set -
attached photos
6/26/13 - More plant material arrived on site
6/27/13 - Preparation front parking area begins, Columbians &
Trumpet Vine planted along pathway between MI-I & Dog Pen.
Irrigation installed in all planted areas - attached photos
I Total Est. Cost
Notes
X
Photo
i5/1/13
4/27/13 - JE approved
- Unable to move forward until Project 22 - Landscaping
has been resolved
6/1/13 - Brice to review with Aspen about location etc.
6/7/13 - Awaiting electrical proposal due 6/29/13
Landscaping - In House -
t
End
Total Est. Cost
Notes
Start
Ponderosa Pines at Front Entrance &
6/3/13
4/27/13 - JE approved the removal of dead pine in courtyard &
!Photo
Landscape Lights at MH
Ponderosa Pines, Landscape Lights & relocate Pinions to the area.
6/3/13 - Project Started
'6/7/13 & 6/18/13 - Removal of Ponderosas & Pine complete
6/25/13 - Work to begin on landscape lighting
6/29/13 - Have installed landscape lighting where planting is
complete, will continue next week
EFTA01124657
Zorro Projects - 6/29/13
Terraces (27) - Three B's
Terraces - $52,000.00
Stucco/Gutters/Painting - $4,200.00
Start
End
4/7/13
Total Est. Cost
Notes
$56,200.00
12/12/12 - Bid Received
3/20/13 - JE approved
4/7/13 - Project Started
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
5/31/13 - There was a fault in one of the rolls of material, vendor
ihas reordered, will recover area once on site.
6/7/13 - Material on site, will continue 6/10/13
6/14/13 - Membranes & Gutters Complete - attached photos
6/18/13 - Stucco & Painting scheduled to start
6/21/13 - Stucco & Painting Complete - attached photos
16/24/13 - Final review of completed work
7/2/13 - Final Punch Out to begin of all outstanding work
Front Gates Openers Call Boxes (30) -
Start
End
Total Est. Cost
Notes
4/20/13 - Bid received, requested vendor to make adjustments
5/9/13 - Received revised bid. Options & Equipment reviewed
5/12/13 - Options & Equipment selected, final bid due 5/21/13
5/21/13 - Final bid received via fax, unable to read, vendor will
resend.
6/8/13 - Final bid attached, also forwarded separately to RK.
i6/11/13 - RK requested material breakdown
6/14/13 - Material breakdown forwarded to RK
6/19/13 - Resubmitted revised pricing to RK - awaiting direction
6/28/13 - RK requested that Three B's submit an estimate for this
work. Have contacted Three B's, will be on site next week to
review
Photo
Photo
EFTA01124658
Zorro Projects - 6/29/13
Cooling Tower (36) -113H
Replacement of Pool Pac (33) -
Engineering Inspection - $9,100.00
Unit Cost - $43,170.00
Camera Ducting Inspection - $1,214.91
Ducting - TBA
Start
End
Total Est. Cost
Notes
4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded, awaiting confirmation
6/20/13 - Unit on site - attached photo
6/21/13 - Noting attached E Mail, JBH have pulled their team off
moving forward with this project until RK makes contact about
outstanding balance
Payment received by Vendor
7/8/13 - Installation scheduled
Start
End
Total Est. Cost
Notes
9/11/12
4/29/13 - Quote forwarded to RK, who requested more detail
5/8/13 - Revised quote forwarded to RK, awaiting direction
5/22/13 - Beaudin Ganze on site to review project
5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera.
Photo
Photo
16/3/13 - JBH forwarded estimate
6/4/13 - JE approved moving ahead
6/11/13 - JBH due on site
6/12/13 - JBH on site, completed camera inspection, awaiting
report/disc.
6/21/13 - Report/Disc forwarded to Beaudin Ganze, awaiting
report
7/8/13 - Report due 7/8/13
Start
End
Total Est. Cost
Repair Pool/Spa (29)-
Notes
Photo
$12,600.00
5/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
iJE requested work be completed in Sept
EFTA01124659
Zorro Projects - 6/29/13
Water Sample of Tap Water-
Start c End
Total Est. Cost
Notes
Photo
6/12/13
4/27/13 - JE requested water samples be taken.
This will be completed once water system is balanced
5/10/13 - Dakota RO is down, pressure issues
6/2/13 - All Wells up and running
6/12/13 - Water samples taken. Results due back 7/3/13
Exterior Doors Main House - Three B's
Start
End
Total Est. Cost
Notes
Photo
4/27/13 -JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
7/2/13 - Final Punch Out to begin of all outstanding work
Audio Upgrade - in House
Start
End
Total Est. Cost
Notes
Photo
New TV's
DVD Players/Theater Upgrade
6/3/13
Installed - final programming required
Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before moving
forward
5/24/13 - Receiver on site
6/3/13 - Work to begin
6/7/13 - Work 80% complete in Gym, Breakfast Rm, Lodge & BH
6/12/13 - Gym, Lodge & BH Systems Complete
6/14/13 - Will exchange the Samsung DVD for a Marantz DVD in
Breakfast Rm
6/22/13 - Awaiting delivery of Marantz DVD
6/27/13 - Unit has shipped
End
Kitchen Table Electrical - (35)- Three B's
Start
Total Est. Cost
Notes
Photo
Electrical & Data Cut In - $2,160.00
6/3/13
3/1/13 - Bid received Lead Time 1 Week
6/3/13 - Project Started
6/7/13 - Under floor conduit due to be completed 6/12/13
6/13/13 - Conduit installed, tiles replaced & grouted. Cat 5 still to
be pulled and punched down
EFTA01124660
Zorro Projects - 6/29/13
Media Room Curtains (24) -
Start
End
Total Est. Cost
Notes
photo
Blackout & Rings
'2/24/13
End
$6,262.08
4/27/13 -JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Sarah's Office Curtains (25) -
Start
Total Est. Cost
Notes
Photo
Lined & Rings
2/24/13
$2,527.01
4/27/13 -JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yardage
I of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
gym - Mirrored Doors - Three B;.,
Start
End
Total Est. Cost
Notes
Photo
2/24/13
3/4/13 - Project Complete. JE requested further work, which will
begin once Project 27 - Terraces complete
7/2/13 - Final Punch Out to begin of all outstanding work
Phones Main House (31) -
Start
End
Total Est. Cost
Notes
Photo
4/27/13 - JE approved installation of new phones at MH
Awaiting for service provision & estimated cost of delivery of
services - Project 21 Microwave & IT
6/22/13 - Awaiting response from Southwestem Wireless on FCC
License Application & Router at MH
6/28/13 - Requested RK to forward deposit
Phones Ranch Central (35)-
Start
End
Total Est. Cost
Notes
Photo
6/21/13 - Will forward proposal for phone system by 6/28/13
6/27/13 - Project On Hold until Microwave solution resolved
EFTA01124661
Zorro Projects - 6/29/13
Microwave & IT - (21) -
Start
End
Total EA. Cost
Notes
Photo
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 - JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded details of RSM Craig
Franck. Brice has been in contact with Craig will forward details
5/24/13 - Received bid from Southwestern Wireless, have call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK & JR
6/8/13 - Forwarded TW Telecom Proposal for Delivery of Services
to JE & RK. Firm Bids due by 6/14/13
6/14/13 - Received bid from Southwestern Wireless, confirming
details before forwarding
6/15/13 - informed JE, will forward once all details confirmed
6/20/13 - JE approved South Western Wireless bid. RK to
negotiate final bid
6/27/13 - Southwestern Wireless unable to delivery bundled Tl
6/28/13 - Looking into options
Cell Repeaters & Wi-Fi - In House
Start
End
Total Est. Cost
Notes
Photo
Cell Repeater - Library
Will have installed when time allows
Cell Repeater - Gym
Will have installed when time allows
Computers -
Start
End
Total Est. Cost
Notes
Photo
Lap Top - Lodge
Requesting Approval to Purchase
Desk Top - RC Office
Requesting Approval to Purchase
Well K (37)-
Start
End
Total Est. Cost
Notes
Photo
Plugging First Hole
$15,000.00
Estimate to plug 1st hole
Lodge Roof
Start
End
Total Est. Cost
Notes
Photo
Repair/Replace Broken Sections
Three B's will complete after summer visit
EFTA01124662
Zorro Projects - 6/29/13
Yurt - (23) -
Start
End
Total Est. Cost
Notes
!Photo
Replacement Walls/Roof/Door/Windows
5/9/13
$6,355.00
plus shipping
charges of
approx.
$480.00
4/27/13 - JE approved investigating options
5/9/13 - Project Request forwarded to RK & JE
5/9/13 -JE approved Project, awaiting direction on deposit
payment from RK
5/13/13 - Deposit forwarded to vendor $3,177.50
Removal of furniture, deconstruction of existing
walls/roof/windows & door. Then reconstruction of base,
resanding/sealing floor required -in house
7/3/13 - Scheduled Ship Date
Start
Repair/Painting Work- Ion
End
Total Ed. Cost
Notes
Photo
Start
5/7/13 - E Mailed Photos to JE showing work required
5/23/13 - Forwarded all work details to Ion, including work that
will be required after MBR Terrace is completed.
6/29/13 - Additional work - sign on Adobe
End
Total Est. Cost
Painting/Staining/Sealing - In House
Notes
Photo
Stables - including outside/inside lights
Work to begin once MH projects complete
Adobe - including wooden deck & front
Work to begin once stables complete
Log Cabin
Work to begin once all painting/staining projects complete at RC
Lodge
Work to begin once all painting/staining projects complete at RC
T
Reservoir
Work be begin once all painting/staining/sealing projects complete
Fuel Storage Tanks
Work to begin once all painting/staining/sealing projects complete
RC Office Interior
Work scheduled for Winter
RC Mechanical Bays - interiors
Work scheduled for Winter
RC Garages - interiors
Work scheduled for Winter
EFTA01124663
Zorro Projects - 6/29/13
Ext Doors Main Compound - In House
Start
End
Total Est. Cost
Notes
Photo
Front, Estancia, Mech, Garage, Pool Doors 6/24/13 6/28/13
$60.00
6/24/13 - Project Started - refurbish & waxing all wooden doors
6/28/13 - Project Complete - attached photos
X
Start
End
Fuel Storage Tank Area - In House
Total Est. Cost
Notes
Photo
Removal of grass. Matting & edging to be
installed
Gravel/Edge Work RC Paths - in House
Start
End
Total Est. Cost
Notes
Photo
All paths to be dug out, edged and gravel
to be installed
-- I
End
End
Start
Log Cabin - In House
Total Est. Cost
Notes
Photo
Step Outside - Repair/Replace Broken
Section
Start
Caboose - In House
Total Est. Cost
Notes
Photo
Installation of Retaining Wall
To begin early Fall
4 Bay Garages - In House
Start
End
Total Est. Cost
Notes
Photo
Repair Leaking Roof
To begin early Fall
Repair Damaged Wall
Pole Barn Water Truck Parking
Start
End
Total Est. Cost
Notes
Photo
Installation of a Retaining Wall
To begin late Fall, Early winter
Cattle Gates/Guards x 3 - In House
Start
End
Total Est. Cost
Notes
Photo
Refurbishment, Empty & Paint
To begin early Fall
Start
End
Total Est. Cost
Cactus Removal - In House
Notes
Photo
Start
To begin late Fall, early Winter
Tilt Trailer - In House
End
Total Est. Cost
Notes
Photo
Refurbish/Paint
Winter Project
EFTA01124664
Zorro Projects - 6/29/13
Vehicles
Start
End
Total Est. Cost
Notes
Photo
2013 Ford Expedition - review Captain
Seats to be Installed
3/27/13
5/2/13 - Estimate received - $11,528.74
5/31/13 - as of date unable to get a 2nd estimate,
I
ft E
Start
End
Total Est. Cost
Notes
Ph
oto
4/27/13 - JE approved investigating purchase of 2 dogs.
Researching
Inventorv/dean Work Shops-In House
Start
End
Total Est. Cost
Notes
Photo
6/6/13
6/20/13 - Landscaping, Paint & Wash Bay 90% complete -
attached photos. All these location will be painted over the winter
6/21/13 - Work continues as time allows - complete clean up &
inventory of all work shops at RC & MH
6/29/13 - Landscaping, Paint, Irrigation & Wash Bay Complete.
Welding, Woodshop, Mech Shop 80% complete
Purchases
Start
End
Total Est. Cost
Notes
Photo
Outside Pool Furniture
Investigating Options
Pool Pace Clock
7/10/13 - Due on site
Large Chrome Pool Clock
Investigati
Options
Facial Machine
to purchase
Wells - Dakota & K
Combined Usage as of date 6/14/13
8.03 afa
2014 Budget
Bunkhouse
Start
End
Total Est. Cost
Notes
Photo
Window/Doors - Total Replacement
EFTA01124665
Technical Artifacts (4)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Wire Ref
RefurbishWire Ref
RefurbishmentWire Ref
referenceWire Ref
refurbishForum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.